Quarterly Activities and Annual Reserves Report
Released
Released
Announcement PDF
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 1 of 14
Key Activities & Highlights 30 January 2026
Australis Oil & Gas
Limited
ABN: 34 609 262 937
ASX: ATS
Australis is an upstream oil
and gas company seeking
to provide shareholders
value and growth through
the strategic development of
its quality onshore oil and
gas assets in the United
States of America.
The Company’s acreage
within the core of the oil
producing TMS provides
significant upside potential
for ATS with 62 million bbls
of 2P+2C net reserves and
resources including 165
thousand bbls producing
reserves1,3
.
The Company was formed
by the founders and key
executives of Aurora Oil &
Gas Limited, a team with a
demonstrated track record
of creating and realising
shareholder value.
Address
2nd
Floor, 215 Hay Street
Subiaco, WA 6008
Australia
Suite 3680
3 Allen Center
333 Clay Street
Houston, Texas
U.S.A 77002
Contact
Telephone:
+61 8 9220 8700
Facsimile:
+61 8 9220 8799
Email:
[email protected]
Web:
www.australisoil.com
Australis holds a material and scalable position within the high quality
and delineated core of the largely undeveloped Tuscaloosa Marine
Shale (TMS) which has been validated by recently announced
transactions
Significant Transactions Achieved4
Secured a Development Partner that is an established US listed
independent oil and gas company with a multi-billion dollar enterprise value
and active onshore development and exploration operations in multiple US
unconventional basins
Development Partner has the right to deploy up to US$46 million of
development capital for new wells in the TMS, carrying Australis for a 20%
working interest, to earn 80% working interest in Australis’s undeveloped
TMS Core acreage
Financing Transaction with EQV Group (“EQV”) whereby it acquired 90% of
Australis’ interest in producing wells for US$16.9 million before closing
adjustments
Operations and Financial Summary – 4th quarter 2025
Sales volume of 48,900 barrels (WI) (no change vs Q3 2025)
Lower WTI pricing (-12% vs Q3 2025) partially offset by hedge gains led to
lower sales revenue of $3.0 million (-9% vs Q3 2025)
Production expenses unchanged compared to previous reporting quarter but
four workovers in October led to higher total operating costs (+20% vs Q3
2025)
The combination of lower sales revenue and higher operating costs led to a
reduced Field Netback of US$0.4 million (-64% vs Q3 2025)
Macquarie Credit Facility was repaid in full from the proceeds of the EQV
Financing Transaction
Cash balance at quarter end of US$14.2 million (+330% vs Q3 2025) and
no Macquarie Facility debt (-100% vs Q3 2025)
Year End 2025 Reserves Update
Ryder Scott Company, LP have completed their independent assessment of
YE25 reserves and resource estimates1
with an effective date after the
completion of the EQV Financing Transaction
Australis PDP reserves of 124 Mbbls with an NPV(10) of US$2.4million1
Australis 2P + 2C mid case recoverable estimate 62 MMbbls1,3
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 2 of 14
KEY FINANCIAL INFORMATION
The following table summarises key financial metrics for Q4 2025 and provides a comparison to Q3
2025.
Table 1: Q4 2025 Key Metrics
Key Metrics Unit Q4 2025 Q3 2025
TMS Core Land (Net) acres 47,200 47,300
Net Oil resource (2P + 2C) MMbbls 621,3
652,3
Sales Volumes (WI) bbls 48,900 48,800
Average Realised PriceA
US$/bbl $59.74 $67.67
Average Achieved PriceB
US$/bbl $62.22 $67.87
Sales Revenue (WI)B
US$MM $3.0 $3.3
Sales Revenue (Net)B
US$MM $2.5 $2.7
Field Netback US$MM $0.4 $1.1
Field Netback / bbl (WI)B
US$/bbl $ 8.8 $22.3
Field Netback / bbl (Net)B
US$/bbl $ 11.0 $27.7
Adjusted EBITDA8
US$MM -$ 0.2 $0.2
Cash Balance (Qtr end) US$MM $14.2 $3.3
Total Debt (Qtr end) US$MM $0 $4.8
A
excludes effect of hedge contracts settled
B
includes the gain from the settlement of hedge contracts of US$0.12 million (Q3 2025:
gain of US$0.01 million)
TMS PRODUCTION AND OPERATING PERFORMANCE
During the previous quarter there were no workovers carried out, however during October 2025
Australis undertook four workovers (on the Mathis 29-32H-01, Ash 13H – 02, Stewart 30H – 1 and
Reese 16H – 1) with the wells restarting production by the end of October. The successful workover
campaign was accomplished at a cost ~30% below cumulative AFEs.
The total workover count for 2025 was seven wells, with total costs significantly below budget which
is further testimony to the excellent work undertaken in design, execution and operation of the
producing wells by the production team.
Despite the wells shut in ahead of the workover program, sales volumes were effectively unchanged
quarter-on-quarter although lower WTI pricing led to reduced revenues and this, together with the
incremental workover costs, were the primary contributors to reduced Field Netback and Adjusted
EBITDA this quarter.
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 3 of 14
FINANCE AND CORPORATE
Cash and Capital
Results for the quarter include:
• Sales Revenue (WI) (after hedges) of US$3.0 million, 9% lower than the previous period due
to lower realised WTI pricing;
• The Company’s cash position was improved by the receipt of a US$1 million option fee from
the Development Partner on execution of the Development Transaction and US$15.6 million
after closing adjustments from the sale to EQV;
• Field Netback reduced by 64% compared to the previous quarter to US$0.4 million, primarily
due to lower revenue and the workover costs incurred during the quarter, but also included
an inventory adjustment relating to the disposal of 90% of Australis’ interest to EQV on 30
December 2025; and
• Australis fully repaid the Macquarie Credit Facility in the quarter and has a cash balance of
US$14.2 million at the end of the quarter.
Credit Facility
Operational cash flow during the reporting quarter paid for interest costs and the monthly Facility C
amortisation payment under the Macquarie Credit Facility in October and November. On 30
December 2025, the outstanding Facility A and C loans, plus unpaid accrued interest for December,
was fully repaid from the proceeds of the EQV Financing Transaction. At the same time Macquarie
Bank released their security over Australis assets and bank accounts.
Oil Price Hedging
During the reporting quarter Australis realised a modest hedge gain of US$0.12 million compared to
a gain of US$0.01 million in the previous quarter primarily due to the average realised WTI oil price
being $7.93/bbl (12%) lower in Q4.
Following the close of the EQV Financing Transaction and repayment of the outstanding Macquarie
Facility loans Australis also took the opportunity to close out all outstanding swap hedges that were in
place either as part of the Facility C arrangements or those based on the production profile prior to
the EQV divestment. In total Australis closed out 24,300 bbls of swaps at various prices, which
generated a payment to Australis of US$76,000 after costs.
Australis has retained existing collar hedges of 1,000 bbls/month for January to April 2026 having a
floor price of US$60/bbl WTI, which equates to approximately 60% of our expected reduced WI
production during this period. Australis will continue to review its hedge program and position from
time to time, including when the Development Partner elects to drill new wells as part of the
contemplated carry program.
The table below summarises the protected WTI floor prices and the ceiling prices for all hedged
volumes on future production at the end of the reporting quarter.
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 4 of 14
Month Quantity (bbl)
Protected
price
US$/bbl
Ceiling price
US$/bbl
Jan 2026 1,000 $60 $71
Feb 2026 1,000 $60 $68
Mar 2026 1,000 $60 $67
Apr 2026 1,000 $60 $67
Table 2 : ATS hedge position as at 1 January 2026
TMS Lease Position
Australis has continued to manage its lease position in a disciplined fashion, whilst being cognisant of
cash reserves and working capital obligations. During this reporting period Australis extended 1,190
net acres for one year that were due to expire and, following execution of the Development Agreement
with the Development Partner, a further 1,990 net acres were similarly extended.
As at 31 December 2025 Australis holds ~47,200 net acres in the TMS Core, of which ~39,900 net
acres (85%) are HBP.
Australis is working with the Development Partner to deploy the US$1 million secured as part of the
Development Agreement for an initial lease program4
, which can be used for both direct leasing and
lease options.
Figure 1 below provides more detail on the expiry profile of the TMS Core acreage position as at 31
December 2025. Figure 2 (see “About Australis” section below) provides a map of the Australis
acreage position.
Expiration Year – TMS Core Net Acres
Figure 1 : Expiry profile of ATS TMS acreage
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 5 of 14
Business Development and Corporate Strategy
In the quarter, Australis successfully completed two transactions4
to achieve a number of corporate
objectives that management have sought to address for some time.
Partnered in the TMS with an established and aligned US-listed independent oil and gas
company with onshore development and exploration operations in multiple unconventional
basins.
The application of up to US$46 million of development capital for new wells in the TMS from the
Development Partner (“Carry Program”), including funding Australis for a 20% working interest
in that program, in order to earn an 80% working interest in undeveloped HBP acreage and
Term leasehold of approximately 46,100 net acres.
Australis and the Development Partner have formed an Area of Mutual Interest (“AMI”) within
the TMS Core area, allowing Australis to participate at a 20% working interest in leasing activity
and rebuild its position within the target area following a successful earn-in by the Development
Partner. The Development Partner to carry Australis for its 20% working interest for the initial
US$1 million of leasing within the AMI.
Australis has monetised 90% of its working interest in the TMS producing well inventory through
the sale to EQV, allowing the repayment of all outstanding Macquarie Facility indebtedness and
increasing the cash balance to US$14.2 million.
Australis is therefore funded to participate in the Development Partner leasing program, is
carried on a work program of up to US$46 million and has capacity to fund its working interest
in future wells when the Carry Program is completed.
The Development Partnering Transaction was executed on 25 November 2025 and included an up-
front payment of US$1 million to Australis in addition to the US$1 million initial leasing program
commitment. For more details on the deal terms please refer to the relevant announcement4
. Since
execution Australis has been working with both the subsurface and land departments of the
Development Partner on planning and preparation for the Carry Program.
The EQV Financing Transaction was closed on 30 December 2025 (see separate announcement5
).
EQV assumed field production operatorship from Australis and acquired 90% of the Australis working
interest in all Australis operated wells. Australis will provide transition services to EQV for the next
60 – 90 days, during which it will continue to manage the various aspects of operations and
administration for a fee.
YEAR END 2025 RESERVES AND RESOURCE UPDATE
Australis is pleased to provide its Year End 2025 (“YE2025”) reserve and resource update as
independently assessed by Ryder Scott Company, L.P (“Ryder Scott”) with an effective date of 31
December 20251
and detailed in the report issued on 29 January 2026.
The EQV Financing Transaction closed on the 30 December 2025 and so the YE2025 reserve and
resource estimates are based on Australis having divested 90% of its interests in the operated
producing well inventory.
As there remains some uncertainty on development activity timing Australis has continued to assess
reserves for the producing assets only, with the undeveloped position being considered a contingent
resource. As the Development Partner only earns an 80% interest in the Australis undeveloped
acreage when the Carry Program is complete, the contingent resource estimates in the YE2025 report
reflect 100% of the Australis acreage at the report effective date.
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 6 of 14
Table 3 below provides the detail of the YE2025 reserve estimates and a comparison to YE2024
following the divestment of 90% of our working interest (Note the estimates below are all net reserves,
i.e. after royalty interests).
Reserve Category
Australis Reserves1 Net Oil
YE2025
vs
YE20242
Gross Oil
(Mbbls)
Net Oil
(Mbbls)
Proved Developed Producing (PDP) 1,928 124
Proved Developed Not Producing (PDNP) 45 4
Proved Developed (1P) 1,973 128 -92%
Probable Developed Producing 579 36
Probable Developed Not Producing 4 0
Probable Developed Total 583 37
Proved + Probable Developed (2P) 2,556 165 -92%
Possible Developed Producing 767 48
Possible Developed Not Producing 3 0
Possible Developed Total 770 49
Proved + Probable + Possible Developed (3P) 3,326 214 -92%
Table 3 : ATS YE2025 Reserve Summary
The NPV(10) of the net PDP reserves volume is US$2.4million1
, which is a decrease of -94% from
the YE2024 value2
, predominantly due
The sale of 90% working interest to EQV,
The reduced oil price used for the analysis of US$67.53 which was a US$10.21 reduction
(13%) compared to last year, and
The produced volumes during 2025 reducing reserves.
Table 4 below provides the detail of the YE2025 resource estimates and a comparison of oil volumes
to the YE2024 estimates.
Contingent Resource
Category
Oil
(Mbbls)1
Oil
YE2025 vs
YE20242
Gas
(MMscf)1
BOE
(Mboe)1
Low Estimate (1C) 19,709 +2% 7,935 21,032
Best Estimate (2C) 62,156 -1% 34,258 67,866
High Estimate (3C) 112,498 -1% 76,041 125,172
Table 4 : ATS YE2025 Resource Summary
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 7 of 14
Assumptions
Key assumptions used by Ryder Scott to generate the YE2025 estimates are as follows:
Reserves and contingent resources estimates are calculated using deterministic methodologies.
The oil price used for all reserves analysis in this report is a flat realised $67.53/bbl, which is
based on the average achieved price by Australis on the first day of the trailing 12 months of
2025.
Operating costs for developed producing wells are based on the average of actuals incurred
between December 2024 and November 2025.
The existing PDP estimates are based on production from 42 well (28 operated and 14 non-
operated wells – 2.8 net wells).
The existing PDNP estimates are based on projected production from 4 operated wells and 2
non-operated wells (0.4 net wells).
The 1P, 2P and 3P figures provided are the arithmetic summation by category and are
referenced to the individual well oil metering at each producing well location.
The 1C, 2C and 3C figures provided are the arithmetic summation by category
Contingent resources are estimated for areas outside of a producing well location. The 1C
contingent resources are limited to any development unit (usually 1920 gross acres) that
contains an existing TMS well which would have been considered as reserves had the
development plan included such locations within the five-year development window. The 2C
and 3C considered all the remaining undeveloped net acreage within the core area but used
different estimates of in-place volumes and recovery factors.
No gas sales are assumed in the reserve estimates as all gas is presently consumed on the
lease, however projected gas volumes are included in the contingent resource estimates which
includes an allocation to existing production and undeveloped acreage.
PDP reconciliation
Table 5 below provides a reconciliation of net PDP reserves between 31 December 2025 and 31
December 2024.
Description
Net Oil
(Mbbl)
PDP Reserve (31/12/24)2
1,624
2025 Net Production -168
Removal of Workover Assumptions -66
Technical Adjustment -104
Lower oil price -27
Operating cost -6
Changes to ownership -1,131
Other 2
PDP Reserve (31/12/25)1 124
Table 5 : Reconciliation of PDP reserves between YE2024 and YE2025.
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 8 of 14
Contributors to the adjustments shown in the above table are discussed below.
During 2025 Australis produced 166 Mbbls of net production
As operator Australis scheduled workovers with associated costs and production improvements,
the impact of which have been removed with non-operator status.
Technical adjustments, both positive and negative, were applied to most of the wells by Ryder
Scott in the YE2025 reserve estimate. The Lawson 25H-1 and Sabine wells had larger
reductions applied.
Lower oil prices of US$67.53 (2025) vs US $77.74 (2024) reducing economic cut off
projections.
Australis sold 90% of its working interest to EQV.
The other changes were not material.
Net Contingent Resource reconciliation
Table 6 below summarises the change in net contingent resource estimated on 31 December 2025
and 31 December 2024.
Description
Net Contingent Resource
31 Dec 20251
(MMbbl)
Net Contingent Resource
31 Dec 20242
(MMbbl)
Low Contingent Resource (1C) 19,709 19,333
Most Likely Contingent
Resource (2C)
62,156 62,560
High Contingent Resource (3C) 112,498 113,233
Table 6 : Comparison of contingent resources for YE2024 and YE2025
There were only very minor changes (+/- 1-2%) to the contingent resource estimates.
All subsurface assumptions on in place volumes and recovery factors remained identical for
both the YE2024 and the YE2025 resource estimates.
All undeveloped acreage was evaluated for contingent resource based on the decision not to
consider a development plan.
There were some minor adjustments in gross acreage assumptions in the contingent resource
estimates for 2025.
The net acreage position decreased by 800 acres during 2025.
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 9 of 14
Appendix 5B
Attached is a copy of the Appendix 5B for the quarter ended 31 December 2025.
This ASX announcement was authorised for release by the Australis Disclosure Committee.
Further
Information:
Ian Lusted Graham Dowland
Managing Director Finance Director
Australis Oil & Gas Australis Oil & Gas
+61 8 9220 8700 +61 8 9220 8700
Ends
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 10 of 14
ABOUT AUSTRALIS
Australis (ASX: ATS) is an ASX listed oil and gas company seeking to provide shareholders value
and growth through the strategic development of its quality onshore oil and gas assets in the
United States of America. The Company was formed by the founder and key executives of Aurora
Oil & Gas Limited, a team with a demonstrated track record of creating and realising shareholder
value.
With approximately 47,200 net acres (85% HBP) within the production delineated core of the
proven oil producing TMS, Australis retains significant upside potential with approximately 160 net
future drilling locations.
At year end 2025 Ryder Scott independently assessed the Australis acreage held at that time with
62 MMbbls of 2P + 2C recoverable volume including 165 Mbbls 2P producing reserves providing
net field cash flow1,3
. The contingent oil resource is only contingent on a qualifying development
program and Australis will carry out a reassessment of its undeveloped reserve position when a
program is agreed with our partner
TMS Assets & Background
The map shown in Figure 2 is a representation of the acreage position that Australis holds within
the TMS Core.
Figure 2 : Location of Australis acreage and TMS wells
The Tuscaloosa Marine Shale is a Cretaceous shallow marine unconventional shale that is present
across central Louisiana and southwest Mississippi. The play is the same geological age as the Eagle
Ford Shale in South Texas and the Woodbine Shale in East Texas.
The play is relatively deep, high pressured and oil weighted. As experienced in most unconventional
plays, early results (2010 – 2014) demonstrated variable production performance and relatively high
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 11 of 14
well costs, driven by initial operational difficulties encountered whilst drilling and completing the
wells. The activity that did take place delineated a core area of the play where production results
were consistent and comparable to other, far more developed, unconventional plays such as the
Eagle Ford and the Permian. This area is shown in the blue oblong in Figure 2 and represents
Australis’ interpretation of the TMS Core.
The comparison of the 2014 production results from the core of the TMS (the 15 wells drilled in the
Australis TMS core leasehold area in 2014 and which comprise the TMS Type Curve) with the three
type curves generated by Ryder Scott for the YE 2020 reserve report is shown in Figure 3 below.
To qualify as a reserve Ryder Scott must assess a future location as economic and the YE 2020
reserve report was evaluated assuming a flat oil price of US$47.02/bbl7
. Note the YE 2023 Reserve
Report1
did not assess undeveloped reserves as any assessment is dependent on a drilling plan for
the next 5 years. Australis made the decision to defer the assessment until a partner is introduced
and a development plan is determined.
Figure 3 : Average oil production of ATS 2014 TMS wells vs Ryder Scott Proved, Probably and Possible Type Curves
and performance of the full length laterals drilled by Australis in 2018
The 2014 fall in commodity price generated the opportunity for the two low cost acquisitions by
Australis in the TMS and for an ongoing cost-effective and strategic leasing program where longer
lease life is targeted together with improved commercial terms. Australis has remained very
disciplined and focused only within the production delineated TMS Core.
The appraisal activity by Encana and other participants in the TMS during 2013/2014 also addressed
many of the operational challenges that were initially experienced. Costs and performance
repeatability were improving, and activity levels were increasing during 2014 until evolution in the
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
0 6 12 18 24 30 36 42 48 54 60
BBL
Oil
Month
Cumulative Oil Production6
RS Possible (700 mbbl) RS Probable (604 mbbl) RS Proved (520 mbbl)
Avg 15 TMS Wells Avg Stewart/Taylor Normalised
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 12 of 14
play was interrupted by the oil price drop in late 2014. As a direct result, Australis is the only
company to have drilled new wells in the play since the beginning of 2015 other than in the last
quarter of 2021, when State Line Exploration successfully drilled and cased their first well in the play.
Consequently, none of the numerous industry improvements that have continued to drive forward the
economics of other unconventional plays have yet been applied to the TMS. The production results
of the full length laterals drilled by Australis in 20186
are also shown above on Figure 3.
GLOSSARY
Unit Measure Unit Measure
B Prefix – Billions bbl Barrel of oil
MM Prefix – Millions boe Barrel of Oil equivalent (1bbl = 6 mscf)
M or k Prefix – Thousands scf Standard cubic foot of gas
/d Suffix – per day Bcf Billion cubic feet of gas
Term Definition
TMS Core
The Australis designated productive core area of the TMS delineated by production
history
WI Company beneficial interest before royalties
Royalty
Interest in a leasehold area providing the holder with the right to receive a share of
production associated with the leasehold area
Net or NRI Company beneficial interest after royalties or burdens
C Contingent Resources (1C/2C/3C equivalent to low/most likely/high)
NPV(10) Net Present Value (@ discount rate)
EUR Estimated Ultimate Recovery of a well
WTI West Texas Intermediate oil benchmark price
LLS Louisiana Light Sweet oil benchmark price
D, C&T Drill, Complete and Tie - in
SOFR Secured Overnight Financing Rate
Opex Operating Expenditure
G&A General & Administrative Expenditure
HBP
Held by production – within a formed unit a producing well meets all lease obligations
within that unit. Primary term remains valid whilst well is on production.
PRB Probable Reserves
PDP Proved Developed Producing Reserves
PDNP Proved Developed Not Producing Reserves
PUD Proved Undeveloped Reserves
Net Acres Working Interest before deduction of royalties or burdens
Field Netback
Oil and gas sales net of royalties, production and state taxes, inventory movements,
hedging gains or losses and field-based production expenses but excludes depletion
and depreciation
Adjusted
EBITDA
Earnings before interest, tax, depreciation, depletion, amortisation expenses and
impairment (see note 8 for reconciliation)
IP30 The average oil production rate over 30 days of production following clean up
YOY Year on year
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 13 of 14
YE Year end
TMS Type
Curve
The history matched production performance of 15 wells drilled in the TMS by Encana
in 2014. Corresponds to an average treated horizontal length of 7,200ft. Refer to the
Appendix of the Australis Corporate Presentation
IDP Initial drilling program of 6 wells in the TMS by Australis commencing late 2018
DUC Drilled uncompleted well
OD Outer Diameter of a tubular
Notes
1. Estimates from the independent Ryder Scott report, effective 31 December 2025 and dated 29 January
2026. The report was prepared in accordance with the definitions and disclosure guidelines contained
in the Society of Petroleum Engineers (SPE), World Petroleum Council (WPC), American Association
of Petroleum Geologists (AAPG), and Society of Petroleum Evaluation Engineers (SPEE) Petroleum
Resources Management (SPE-PRMS) as revised in June 2018. Ryder Scott generated their
independent reserve and contingent resource estimates using deterministic methods. The achieved
price and NPV(10) values quoted are for the project only, they do not include any impact from any oil
price hedges that Australis had entered into at that time.
2. Estimates from the independent Ryder Scott report, effective 31 December 2024 and dated 29
January 2025 which was initially disclosed in the announcement titled "Quarterly Activities Report"
issued on 31 January 2025. The report was prepared in accordance with the definitions and disclosure
guidelines contained in the Society of Petroleum Engineers (SPE), World Petroleum Council (WPC),
American Association of Petroleum Geologists (AAPG), and Society of Petroleum Evaluation
Engineers (SPEE) Petroleum Resources Management (SPE-PRMS) as revised in June 2018. Ryder
Scott generated their independent reserve and contingent resource estimates using deterministic
methods. Australis is not aware of any new information or data that materially affects the information
included in the referenced announcement and all the material assumptions and technical parameters
underpinning the estimates in the original announcement continue to apply and have not materially
changed.
3. The figures quoted is the rounded arithmetic sum of the 2P reserve and 2C resource estimate as
reported in the Ryder Scott reserve reports.
4. Announcement dated 26 November 2025 titled ‘TMS Development Partnering & Financing
Transactions”.
5. Announcement dated 31 December 2025 titled ‘TMS Financing Transaction Completed’.
6. Average production from Stewart 30H-1 and Taylor 27H-1 wells normalized to 7,200 ft completed
horizontal length and adjusted for production curtailments during COVID low oil prices Q2 2020.
7. All estimates and risk factors taken from Ryder Scott, report prepared as at 31 December 2020 and
generated for the Australis concessions to SPE standards. See ASX announcement released on 5
February 2021 titled “Reserves and Resources Update Year End 2020”. Australis is not aware of
any new information or data that materially affects the information included from the referenced
announcement and all the material assumptions and technical parameters underpinning those
estimates from the original announcement continue to apply and have not materially changed.
8. Non IFRS reconciliation to EBITDA
QUARTERLY ACTIVITIES REPORT | 4th Quarter 2025
ANNUAL RESERVES REPORT | 2025
Page 14 of 14
The following table reconciles net loss after tax to Adjusted EBITDA for Q425:
Unaudited
31 December 2025
US$’000
Net loss after tax (22,120)
Adjustments:
Net finance expenses 185
EBIT (21,935)
Depletion & Depreciation 1,015
Impairment 20,681
Adjusted EBITDA (239)
Note that the Impairment value included in this table is calculated in accordance with AASB 136 and
is based on transaction valuations. When assessing the recoverable value of the Australis oil and
gas undeveloped acreage, the only value ascribed was the discounted value of the Carry Program
capital expenditure. There is no allocation for either the value of Australis's working interest in the
carried wells or the development value of the retained acreage after the Carry Program.
Competent Persons Statement
The reserves and contingent resource estimates provided in this announcement pertaining to the Tuscaloosa
Marine Shale is based on, and fairly represents, information and supporting documentation, prepared by, or
under the supervision of, Eric Nelson, P.E., who is an employee of Ryder Scott Company, L.P. an
independent professional petroleum engineering firm. Mr Nelson is a Professional Engineer in the State of
Texas (Registration No. 102286). The reserve and resource information pertaining to the Tuscaloosa Marine
Shale in this ann
Share your feedback